Archive for the ‘Construction Phase’ Category

Going up fast!

Monday, August 1st, 2011

DSC00609DSC00610

DSC00611Building erection is well underway.  This is the part of the project that things begin to look smaller than you expect, but that soon changes, as we all know.  One hundred plus temperatures during the day make the installation of the exterior metal skin an unenviable task, but we have a good crew that works through the heat to keep on schedule.

This project moves forward on a surprisingly fast pace from day to day and the progress is sometimes remarkable.  The second floor mezzanine is framed and will be poured later this week.  First floor light gauge metal framing has begun and small changes are starting to find their way into the layout.  All project partners are watching intently to make sure all the original decisions are still making good sense.

Keep an eye on this one as it’ll change character often!

Touch up

Monday, August 1st, 2011

DSC00608DSC00607DSC00601

The deadline is here and the finish line is, too.  We’ve pushed harder than we thought possible and our team of designers, contractors, sub-contractors, suppliers, installers, delivery people and general laborers have found the drive and determination to get this project finished.  We still have eight additional classrooms to put the finishing touches on, but the administration area and the first four classrooms will be ready for admission as planned.  almost 100 children will have a place to come to school in two weeks.  Now, it’s all about the “touch-up.”

Thanks, team!

Framing

Thursday, July 14th, 2011

Under a typically partly cloudy summer sky, the first parts the new building arrived on site.  The main frame steel, primered the familiar red color (which is why it’s often refered to as “red iron.”) lies on dunnage next to the apparatus bay end of the building.  Along with the framing came bundles of exterior skin and all the pieces and parts for erection.  Once the stab has had a couple of weeks to cure after finishing, we’ll start erecting.  It will move quickly at that point, so visit the site often!

DSC00590DSC00587

The Deadline Looms

Thursday, July 14th, 2011

Sounds ominous, doesn’t it?  It’s really not.  However, the substantial completion date does get closer every day.  The general contractor and the sub-contractors have been doing a great job understanding the keeping up with the end date.  Most all materials have made it to the job site and now it’s in the final push for everything to be installed and in working order.  Our final inspections are coming up as is the walk-through with the local Health Department for licensing purposes.  The exterior landscaping and planting begin next week.  The playground equipment and interior furnishings are beginning to show up.  The final scheduling details are all coming to a head.  Now’s the time with everyone will crowd into the same spaces to finish their portion of the work.

Drive by at the end of next week and you’ll see a building project that is nearing the finish line.  It’s street side facade presenting it’s final look.  It’s an attractive addition to the neighborhood and will be another quality project by The Opportunity Project Charitable Trust!

DSC00593DSC00591DSC00596

Two Rings

Friday, June 17th, 2011

DSC00579Not Lord of the Rings or even a three ring circus, but play rings.  These are the two latest additions to the rear playground at TOP Evergreen.  They are the boundaries of the playground equipment that will eventually be installed.  The first one looks like a reflecting pool but that is because it’s excavated to allow for the appropriate depth of protective “fall zone” material below the equipment.

There are grassy areas that will surround the rings and allow for, not only other equipment, but free play area.  This outdoor space will see more than this first iteration in it’s lifetime.  As the TOP program continues to evolve, outdoor play spaces will likely adapt to become outdoor laboratories and exploration areas for expanded education opportunities.

DSC00583In this photo, you see one of several tests being performed on the interior slab prior to the installation of floor finishes.  This test will help the installer comply with the warranty requirements set by the manufacturer.  This is an important step in the lifecycle performance of the flooring.

Equipment Arrival

Tuesday, June 14th, 2011

DSC00570DSC00571DSC00576Today the air handling equipment arrived on site and were lifted to the rooftop mechanical wells via crane.  There are four wells on different parts of the roof for the four different sections of the building and each well gets it’s own set of roof top units (RTU’s).  The largest  of the units weighs in at 1,300 pounds so placement is critical.  In the first picture you can see one of the wells on the roof still clad in building wrap awaiting siding installation.

Also, the rear yard, which will be the main playground, has been rough graded into the two main equipment rings with the connection sidewalks.  You can see the two areas in the second photo.  Trees and landscaping will complement this western playground making it a great place to play in the summer!

Inside, the kitchen equipment is starting to arrive.  The third photo shows the large fire suppression hood that will be installed above the main cooking area.  It is rather large, as can be seen with three men trying to position it for installation.  I like commercial hoods in large kitchens, but I’d hate to have to install one!  These guys do a great job.  Progress meeting tomorrow.

Footings

Tuesday, May 24th, 2011

DSC00555DSC00557The Halstead Fire / EMS building, which is phase one of a two phase project has sprouted roots, or more correctly, begun footings.  Out of the depths of the east end, stem walls are beginning to appear.  The slope on the site, west to east is about a three foot drop so the stem walls need to be framed to bring the slab up to a uniform height.  Underground connection to a new transformer for the adjacent building has been completed and it’s only a matter of another week before we’ll probably see the slab pour.  Stay tuned…

Blacktop

Tuesday, May 24th, 2011

DSC00548The parking lot got started today.  The base course of asphalt is being laid which means the dust will literally and finally, settle.  Getting parking next to the building will help the trades get in closer to their work and will keep the job site substantially cleaner, not to mention the issue we have with dirt parking and precipitation.  And speaking of precipitation, we’re still hoping for a dry week to get the exterior of the project substantially complete.

As for the interiors, the lids are are installed and the ductwork is being hung.DSC00553 Each trunk will split off into the individual classrooms to supply air.  Once the ductwork is finished, the rooftop units will be installed and we’ll have conditioned space!  Conditioned space means the interior finish can begin to arrive on site for installation.  Cabinets, counters and paint will all be scheduled soon.  The rooms are starting to look complete.

Continuing progress

Thursday, May 19th, 2011

Today was one of our regularly scheduled progress meetings.  It’s nice to hear the construction report that we’re ahead of schedule and everyone is working well together.  There are certainly a lot of trades working in the same spaces, but everything just seems to run smoothly.  I chalk that up to good site management.  Thanks, Alan!

Our parking grading is finishing up so that asphalt base course can be laid next week.  Curbs, gutters and walks are being poured in preparation.  The flat roofs are getting their built-up roofing installed and the drywall lids and attic draft stops are almost complete.  The kitchen equipment is being coordinated with the needed infrastructure and while we’re praying for rain for the state of Kansas and particularly the southcentral area, we’re hoping that it continues to skip our little job site.

P1020275P1020279P1020282P1020283P1020286

Breaking Ground

Thursday, May 5th, 2011

Here’s the latest project under construction.  The City of Halstead, Kansas needs to move the Fire Department / EMS offices and vehicle bays out of the existing City Hall and into their own building.  We’re finally under construction.  As you can see in these photos, the site has been cleared and the initial cut has begun so we can form footings and stem walls.  The project will grow over the next few months as we set a new building next to the existing one, move the Department, and then totally renovate City Hall.  Keep an eye on this project over the next 12 months.  There are some dramatic things happening on Main Street in Halstead, Kansas!DSC00539